Schools upgrade

Next steps

 Install the remaining demountables to the south of the Bush Campus.
 Remove the temporary fencing around demountable work areas as work is completed.
 Continue the construction of Building R including pouring of the on-ground concrete slab and assembly of formwork for the above ground structure.
 Prepare Chatswood Public School for construction including installing fencing around the Lowers, astroturf and carpark. The Pacific Highway vehicle entrance will also be prepared as the main construction access point.
 Main works construction is anticipated to start in mid-2021 following the main works contract award and approval of the compliance reporting

Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s